About

Project Overview

As part of our commitment to provide safe and reliable service to all our customers, New York State Electric & Gas Corporation (NYSEG) proposes the Jennison Transmission Solution (JTS) Project, which would help meet the clean energy goals under New York State’s Climate Leadership and Community Protection Act (CLCPA). Towards that goal, and to address asset condition needs, NYSEG is planning a significant, multi-year electric transmission line project consisting of approximately 49 miles of rebuilt and re-routed electric transmission lines in portions of Chenango and Delaware Counties.

While we are investing in upgrades to meet clean energy goals and the community’s growing energy demands, we are working closely with our neighbors so that improvements are performed safely and with minimal disruption to the environment and the community.

Project Purpose and Need

The JTS includes the rebuild of the Jennison Substation in the Town of Bainbridge, and the rebuild of two existing 115 kilovolt (kV) lines, along with the rebuild/relocation of existing lines to reconnect from the old substation to the new location.

The Project is a multi-faceted solution which addresses not only reliability and resiliency needs, but also critical asset condition issues. This upgrade will enable the integration of increased renewable energy resources into the service provided to New York customers. It would also facilitate satisfying several previously identified Bulk Electric System (BES) reliability needs detailed in prior studies including the 2018 North American Electric Reliability Corporation (NERC) BES Assessment and its subsequent updates. The system reinforcements are designed to improve a wide area of regional reliability in line with the Company’s mission to provide NYSEG customers with reliable energy and a commitment to the well-being of our communities.

Project Scope

The proposed substation work includes the full rebuild/relocation of the Jennison Substation in the vicinity of Mt. Pleasant Road in the Town of Bainbridge.

The proposed electric transmission line work includes:

  • Construction of the rebuilt Line 946, primarily along or at an offset from the existing right-of-way, from the rebuilt Jennison Substation to the East Norwich Substation, in the vicinity of East River Road, running generally south to north in the Towns of Bainbridge, Guilford and Norwich, a distance of approximately 21.4 miles. A portion (approximately 6.7 miles) of the existing Line 946 will be redesignated Line 734 after construction of the North Pond Substation as part of a separate wind project by a third-party developer;
  • Construction of the rebuilt Line 949, along the existing right-of-way, from the rebuilt Jennison Substation to Structure 949/182 (Eastern Terminus) in the Town of Hamden outside of the Fraser Substation in the Town of Delhi, running generally west to east in the Towns of Bainbridge, Sidney, Franklin and Hamden, a distance of approximately 25.4 miles; and
  • The relocation/rebuild of several lines, running a collective 2.3 miles, to reconnect from the old Jennison Substation to the new location, including:
    • Line 818: 0.48miles – 46kV
    • Line 823: 1.06 miles – 46kV
    • Line 756: 0.07 miles – 115kV
    • Line 919: 0.08 miles – 115kV
    • Line 943: 0.13 miles – 115kV
    • Line 954: 0.49 miles – 115kV

Benefits to the Region

  • The Project would alleviate constraints on the local transmission system while paving the way for future renewable generation facilities to connect to the power grid, thus enabling New York State to meet its greenhouse emission reduction goals. 
  • The Project, as well as the renewable generation development it enables, would generate many economic benefits to the community during and after construction.
  • The most direct local economic impact would come from employment and property taxes associated with Project construction and renewable generation. Worker income would be spent locally on goods and services, such as housing, healthcare, and food, while property taxes would support local communities.
  • The upgrades will improve the reliability and resiliency of the entire transmission system.

About the Permitting Process

To construct the Project, NYSEG will need:

  • NYS Public Service Commission – Article VII Certificate of Environmental Compatibility and Public Need, and Approval of Environmental Management & Construction Plan (EM&CP)
  • U.S. Army Corps of Engineers – Federal approval
  • Federal Aviation Administration – Notice of Proposed Construction or Alteration
  • NYS Department of Environmental Conservation – SPDES General Permit for Discharge from Construction Activities
  • NYS Department of Transportation – Utility Work Permit
  • Other permits as may be necessary

Document Library

Title Date
Article VII Guide 11/14/2024
Article VII Flow Chart 11/14/2024
Design With the Community in Mind 11/14/2024
EMF 11/14/2024
Permitting 11/14/2024
Comparison of Underground and Overhead Power Lines 11/14/2024



Project Map

Construction Process

1. Site Preparation

The initial stage of construction involves surveying, clearing vegetation, and providing access roads and crew work areas. Before other project work can begin, vegetation must be cleared from the right-of-way (ROW) to assist crews in creating a safe, level work surface. "Danger trees," those with the potential to fall into the lines, are removed. Survey crews will mark the limits of the ROW, access road locations, future structure locations, and sensitive natural areas. Crews will access sites with existing roads where practical, and where necessary new access roads will be constructed. Timber mats will be used to protect lawns, agricultural fields and other sensitive areas such as wetlands. Strict erosion and run-off controls will be in place and monitored throughout the project.

2. Foundation Work and Structure Construction

Structure types and heights are based on the unique engineering requirements for each structure location. The project will use steel single-circuit monopole structures that will either be directly embedded in the ground or erected on concrete foundations. For structures with foundations, concrete will be delivered to the site by truck. Once foundation work is complete, construction crews will erect the structures within the ROW. The steel monopoles will be transported in sections, assembled on-site using a truck-mounted crane, and then lifted onto their foundations. Embedded structures will be placed into excavations, which will then be backfilled.

3. Wire Stringing

Insulators and attachment hardware will be installed and stringing sheaves (rollers or blocks) attached to the insulators. The conductors (wires) will be strung by attaching the conductor to a steel line and pulled through each structure’s stringing sheaves under tension to keep the conductors well off the ground. Conductor-pulling sites located along the ROW will provide space for tractors, trailers with spools of conductor, and tensioning equipment.

4. Restoration and Recovery

Once the new structures are in place, the existing structures and wire will be taken down and recyclable components recovered. With the conclusion of construction activities timber matting will be removed, the ROW will be cleared of all materials and debris, and the site will then be seeded and monitored until vegetative cover is restored. Any disturbed soils will be stabilized, some areas may have additional vegetative buffers or other landscaping installed. Any impacted local roads will be restored to their original state.


Substation Work

The proposed substation work includes the full rebuild and relocation of the Jennison Substation in the vicinity of Mt. Pleasant Road in the Town of Bainbridge. After new access roads are installed, crews will clear vegetation and commence earth work, including cutting, filling and grading. Following the civil work, the substation pad will be built, allowing for foundations, conduit, and ground grids to be installed (in-ground works). Once a vast majority of in-ground works is completed, the above ground work will begin which involves installation of a control building, steel structures, transformers, and major equipment.

New York State Electric & Gas (NYSEG)

NYSEG operates approximately 35,000 miles of electric distribution lines and 4,500 miles of electric transmission lines across more than 40% of upstate New York. We also operate more than 8,150 miles of natural gas distribution pipelines and 20 miles of gas transmission pipelines. We strive daily to provide safe, reliable service to customers and value to our communities.

Get in touch

T: 1-877-245-6790
E: [email protected]


Ask a question?

Name is a required field
Email is a required field
Street Address is a required field
Question is a required field